冷再生施工和机械租赁业务
筑路架桥,奉献社会;以人为本,不断创新

服务热线

18264104888

新闻中心

首页>>新闻中心冷再生机施工进行碾压时的五点操作

冷再生机施工进行碾压时的五点操作

来源:http://www.tclqgc.com/ 日期:2022-10-24 发布人:
在做好冷再生施工的过程中能够节省很多的沥清、沙石等原料的应用,还能够节约工程项目的時间步骤。那么冷再生机施工进行碾压时的操作是怎样的呢?冷再生机租赁厂家为您讲解。
In the process of cold recycling construction, it can save a lot of raw materials such as asphalt, sand and gravel, and save the time and steps of the project. What is the operation of the cold recycling machine when rolling? The cold regeneration machine rental manufacturer will explain it to you.
(1)整形后,当混合料的含水量为佳含水量(+1%~+2%)时,应立刻用压路机在构造层全宽内停止碾压。直线和不设超高的平曲线段,由两侧路肩向路中心碾时,应堆叠1/2轮宽,后轮需超越两段的接缝处,后轮压完路面全宽时,即为一遍。普通需碾压4~6遍。
(1) After shaping, when the moisture content of the mixture is good (+1%~+2%), the roller shall be used to stop rolling within the full width of the structural layer immediately. For straight lines and flat curved sections without superelevation, when rolling from the shoulders on both sides to the center of the road, 1/2 wheel width shall be stacked. The rear wheel shall exceed the joint of the two sections. When the rear wheel has finished rolling the full width of the road, it is one time. Generally, it needs to be rolled 4~6 times.
(2)严禁压路机在已完成的或正在碾压的路段上调头或急刹车,应保证改进土层外表不受毁坏。
(2) It is strictly forbidden for the roller to turn around or brake suddenly on the completed or rolling road section, and the surface of the improved soil layer shall not be damaged.
(3)碾压过程中,水泥改进土的外表应一直坚持潮湿,如水分蒸发过快,应及时补撒少量的水,但严禁洒大水碾压。
(3) During rolling, the surface of cement improved soil shall always be wet. If the water evaporates too fast, a small amount of water shall be sprinkled in time, but it is strictly prohibited to sprinkle large amounts of water for rolling.
冷再生机租赁
(4)经过拌和、整形的水泥改进土,宜在水泥初凝前并应在实验肯定的延迟时间内完成碾压,并到达请求的密实度,同时没有明显的轮迹。
(4) After mixing and shaping, the cement improved soil should be rolled before the initial setting of cement and within the delay time confirmed by the experiment to reach the required compactness without obvious wheel tracks.
(5)在碾压完毕之前,用平地机再终平一次,使其纵向顺适,路拱和高契合设计请求。终平应认真停止,需将部分高出局部刮除并扫出路外;关于部分低洼之处,不再停止找补,可留待下层施工时处置。
(5) Before the rolling is completed, the grader shall be used for final leveling again to make it smooth in the longitudinal direction, and the crown and height shall meet the design requirements. The final leveling shall be stopped carefully, and the part higher than the local level shall be scraped and swept away; Some low-lying areas will not be repaired and can be left for disposal during the construction of the lower layer.
冷再生机施工进行碾压时的五点操作就讲解到这里了,提醒您对此在使用过程中做好维护保养事项,以免出现问题影响设备质量以及施工质量!更多注意事项的了解就来我们网站http://www.tclqgc.com咨询吧!
This is the end of the five points of operation during the construction of the cold recycling machine. We remind you to do a good job of maintenance during the use of this machine, so as to avoid problems affecting the equipment quality and construction quality! For more information, please come to our website http://www.tclqgc.com Consult!

阅读/ Recommended reading

  冷再生机和路拌机在路面施工及维修中各有其独特的功能和适用场景,它们之间的主要区别体现在以下几个方面:  Cold recycling machines and road mi...

冷再生机出租对道路施工行业的影响 2024-12-18
如何选择冷再生机出租服务 2024-12-16
冷再生机出租:道路施工的新选择 2024-12-11
冷再生机租赁在土壤稳定中的应用与优势 2024-12-09

产品/ Recommended products